August 23, 2022 – Another Longer Term House Going Up

The third tiny home is starting to be built. There will be a total of four homes built on the Huta IDP Community project. I also met with the architect and we hired a builder/contractor for the Velyki Lazy IDP Community Project where we are planning on building 18 tiny homes. Tomorrow they will measure the propery. By the end of this week they will clear and level the first half of the property. Then over the next three weeks we will install the first septic system, a well, hook up the first electrical line, and build the foundation for the workshop. When the community is built, the workshop will be turned into a community center which will include a church plant.